BHS Construction

Building on Excellence, Phase Four:
Library, Links, Climate Control (2006-2008)
The fourth and final phase of the Building on Excellence program was the replacement of the cramped
Originally a new building for a library/media center was planned, but escalating costs led to three rounds of failed bids and multiple redesigns. Finally a $3,088,000 bid was awarded to Gorman Construction of Bartlesville to remodel the
The contract also replaced the
The new library/media center has the capacity to seat two classes and features a dedicated technology area, office, workroom, and audiovisual storage. One of the auditorium's
All remaining 2001 bond funds, collected interest, and donated monies were then put toward climate control renovations in the older buildings. A $3,037,000 bid was awarded to Shiloh Enterprises of Edmond to renovate the heating and air conditioning systems in the 1954 stadium, the 1958 annex, and the classroom areas of the 1939 main building.
Next: 2007 Bond & Other Work